Bima Anggaruci Bhirawa Yudha
University of Jember
Jojok Widodo Soetjipto
University of Jember
Dwi Nurtanto
University of Jember
Keywords: tower crane, evaluation of positioning, total transporting time, efficiency, evaluasi penempatan, total waktu pengangkutan, efisiensi
ABSTRACT
Settling of Tower Crane (TC) will influence efficiency of task served, it will effect to leasing cost and operational cost of TC. This problem is gotten by contractors while they arrange construction schedule. TC's placement isn't exact that due to extend scheduling and cost wasteful. Therefore, TC's settling needs a calculation of TC workload balance in order to minimize duration time. To field observation will be taken an ongoing construction project which is Jember Icon's Project on Gajah Mada street in Jember. Results of these researches shown exactly settling of TC will reduce operational hours and project schedule.